Analysis: South Sudan Oil Flow

Must read

Kenya: 16 students in isolation after interacted with COVID-19 positive classmate

6 people have been isolated who have been interacted with a Form Four student of Muumandu Secondary School, Machakos County tested positive...

SSFA Appoints Helen as Project Manager for the Stars Unite Women’s Football Project

South Sudan Football Association (SSFA) appoints Helen Terso as the Project Manager for the Stars Unite Women’s Football Project.

The killer of three siblings at Rock City in Juba, sentenced to death by Hanging

Babu Emmanuel, the Juba University medical student accused of killing three siblings at Rock City in Juba on 1 August 2020, has...

Juba University students staged a protest over a hike in tuition fees and access restriction

South Sudan’s University of Juba students staged a protest at the University entrance citing the unexpected increment in school fees and access...

South Sudan exports its crude oil via pipeline from Hegleig and Paloch to Khartoum and then to Port Sudan. To keep the oil flowing, it has invited international companies to participate in investment opportunities in its refining and infrastructure sectors.  

South Sudan’s economic lifeblood is intertwined with that of Sudan. Both nations are oil-dependent, but South Sudan maintains the bulk of the region’s 3.5 billion barrels of proven oil reserves, while Sudan owns the export pipelines, the refineries, and sea access. One is useless without the other. Based on that interdependency, the two nations signed an agreement in 2012 under which South Sudan would compensate Sudan for the loss of oil production revenue and for the destruction of pipeline infrastructure caused by the civil war.  

The compensation was agreed to amount to USD $3 billion, to be paid as a fee per barrel of oil produced, while the reconstruction of the oil infrastructure is expected to cost up to $1.5 billion according to the South Sudanese Petroleum Ministry.

Initially designed to last for three and a half years, the Transition Financial Arrangement was extended in 2016 to reflect the collapse in oil price and global demand. In December 2019, the document was once again extended for a three-year period, set to end by March 2022.

It establishes that South Sudan should pay $26 for each barrel transported through the Greater Nile Pipeline (GNP), operated by Petrolines for Crude Oil Ltd., and $24.1 for each barrel that passes through the Petrodar Pipeline, operated by the Bashayer Pipeline Company.   

These fees include the actual crude oil transport costs and a $15 per barrel fee that corresponds to the $3 billion South Sudan must compensate Sudan for. After 2022, if no further extensions are needed, the cost per barrel should come down to $9.1 and $11 for the GNP and Petrodar pipelines respectively, reflecting the conclusion of that payment. The agreement also states that South Sudan must supply as much as 28,000 barrels of crude oil per day to the Khartoum refinery.  

Another Path  

Despite improved relations, dependency on Sudan’s oil infrastructure remains a risk and South Sudanese leaders wish to have alternatives. Hence, the country joined one of Africa’s biggest infrastructure developments; the Lamu Port-South Sudan-Ethiopia Transport Corridor project (LAPSSET), which is a multi-billion-dollar project spearheaded by Kenya to create a transport corridor for oil and other commodities.  

The oil pipeline alone is expected to cost up to $4 billion. While the project seemed to have stalled over the last few years, in January 2020, LAPSSET received its biggest support yet, when the African Union announced it was adopting the project as its own, stating it would even be extended to form a continent-wide corridor connecting to Kribi Port in Cameroon.

The African Development Bank, the United Nations Economic Commission for Africa and the African Union’s New Partnership for Africa’s Development are all involved in promoting its implementation.  

It is, however, uncertain how long the project will take to materialize and no new target date has been given for its conclusion. Currently, the COVID-19 outbreak has forced the suspension of the second stage of the land surveys in Kenya, meant to assess the compensations needed for the land used for the pipeline.  

- Advertisement -

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest article

Kenya: 16 students in isolation after interacted with COVID-19 positive classmate

6 people have been isolated who have been interacted with a Form Four student of Muumandu Secondary School, Machakos County tested positive...

SSFA Appoints Helen as Project Manager for the Stars Unite Women’s Football Project

South Sudan Football Association (SSFA) appoints Helen Terso as the Project Manager for the Stars Unite Women’s Football Project.

The killer of three siblings at Rock City in Juba, sentenced to death by Hanging

Babu Emmanuel, the Juba University medical student accused of killing three siblings at Rock City in Juba on 1 August 2020, has...

Juba University students staged a protest over a hike in tuition fees and access restriction

South Sudan’s University of Juba students staged a protest at the University entrance citing the unexpected increment in school fees and access...

Misspelt word on billboard sparks outrage in Fort Portal

A misspelt word on a billboard erected in Fort Portal Tourism city has sparked controversy amongst the locals in the area. The billboard,...